o:id 71177 url https://islam.zmo.de/s/westafrica/item/71177 o:resource_template Newspaper article o:resource_class bibo:Article dcterms:title Travaux du Barrage de Kandadji : Le cap de 2025 est maintenu pour la fin des travaux de la ligne haute tension 132 Kv dcterms:creator https://islam.zmo.de/s/westafrica/item/69178 Ismaël Chékaré dcterms:publisher https://islam.zmo.de/s/westafrica/item-set/62021 Le Sahel dcterms:contributor https://islam.zmo.de/s/westafrica/item/858 Frédérick Madore dcterms:date 2024-03-14 dcterms:type https://islam.zmo.de/s/westafrica/item/67396 Article de presse dcterms:identifier iwac-article-0009976 dcterms:source https://islam.zmo.de/s/westafrica/item/67741 Wayback Machine dcterms:language https://islam.zmo.de/s/westafrica/item/8355 Français dcterms:rights In Copyright dcterms:spatial https://islam.zmo.de/s/westafrica/item/13837 Chine https://islam.zmo.de/s/westafrica/item/490 Niamey bibo:shortDescription L'Agence du Barrage de Kandadji (ABK) a accueilli une mission de la Banque Islamique de Développement (BID) pour suivre l'avancement du Programme Kandadji. Le président de l'ABK a visité le chantier de la ligne haute tension Kandadji-Niamey, financée par la BID, dont les travaux sont à 60% et prévus pour 2025. Bien que les travaux de génie civil du barrage aient été unilatéralement suspendus par une entreprise chinoise, leur reprise est attendue sous condition de garantie. La construction de la centrale hydroélectrique progresse normalement, et l'ABK assure la sécurité de la zone et l'engagement des partenaires financiers. fabio:hasURL https://web.archive.org/web/20241008183109/https://www.lesahel.org/travaux-du-barrage-de-kandadji-le-cap-de-2025-est-maintenu-pour-la-fin-des-travaux-de-la-ligne-haute-tension-132-kv/ --